    The UK Round 1 & 2 offshore wind projects have been extended with an additional 2 GW by the UK Crown Estate.
  • Renewable energy project monitor
    July/August 2011: This second monthly column, written by the ceo of the Energy Industries Council, reports on the latest new project developments in the global renewable energy marketplace.
  • Offshore Wind: Which comes first – The developer or the supply chain?
    The offshore wind industry is facing a massive ramp up ahead of Round 3 developments in the UK. But with few developers setting up shop in the UK and a hesitant supply chain waiting on firm orders before investing in upgraded facilities, will Round 3 deliver on time, and on budget? Renewable Energy Focus’ Kari Williamson travelled to one potential cluster in North East England.
  • SSE Kintyre offshore wind farm halted
    Scottish and Southern Energy has decided to focus on the development of the Islay wind farm site instead.
  • Wind turbine producers step into ten league boots
    Wind turbines are getting bigger, driven by economies of scale and the need to increase ‘power per tower’ at wind farms, especially offshore. George Marsh explores the megaturbine seascape.

Top 5 Stories

News

UK Crown Estate offers area extensions to Round 1 & 2 offshore windfarms

10 August 2009

The UK Crown Estate plans to offer Round 1 and 2 offshore windfarm operators with offshore wind projects in operation, under construction or awaiting construction, the opportunity to apply for area extensions.

The purpose of the area extension offer is to “realise additional offshore wind capacity which could be brought into operation ahead of Round 3 projects,” the Crown Estate says.

The following criteria will form part of the application process:

  • To be eligible to apply for an offshore wind area extension the original project must, as a minimum, have submitted site consent applications;
  • The proposed extension must share a substantial part of one or more boundaries with the original offshore wind site;
  • The extension proposal must demonstrate synergies with the original site, e.g. of construction, operation, improvement of economics and / or grid connectivity;
  • The extension must be capable of delivery in a short timescale;
  • No maximum size of extension is set. However, the scale of the extension should be appropriate to the scale of the original offshore windfarm site taking into account environmental and other constraints.

Offshore wind developers have until 9 September 2009 to register initial interest.

Maria McCaffery, Chief Executive at the British Wind Energy Association (BWEA), comments: “This most welcome announcement underpins confidence in the sector, and shows commitment to further growth of offshore wind. The UK now leads the world in installed offshore capacity and the technology is set to contribute significantly to the country’s energy needs.”

Round 1, launched in 2000, was intended to act as a ‘demonstration’ round, enabling prospective offshore wind developers to gain technological, economic and environmental expertise. Of the 17 projects originally allocated, 7 are now fully operational and 4 are currently under construction, the Crown Estate says.

A competitive tender process for round two sites was launched in 2003. The 15 successful projects awarded Crown Estate Agreements for Lease amount to 7.2 GW and include sites within and beyond territorial waters.

 