Share

Related Links

Related Stories

  • Siemens installs offshore wind grid link for DanTysk
    Siemens will install a grid connection for DanTysk offshore wind farm, part of the SylWin offshore wind farm cluster in the North Sea for TenneT.
  • Remote controlling wind
    The increase in wind power coming onto the grid has seen network operators get much tougher on generators.
  • Offshore wind – do we have what it takes?
    According to analyst Emerging Energy Research (EER), the global installed offshore wind base is expected to grow to nearly 45 GW in 2020. But how far are we away from the technology and supply chain to reach that goal? Renewable Energy Focus' Kari Larsen investigates.
  • Rise of the superconductor, Part 2
    In the ‘Rise of the superconductor’, we highlighted the use of superconductor technology and its potential to transform the economics of wind power. In Part 2, Jack McCall of AMSC outlines how superconductors could help the USA get to grips with its grid modernisation issues.
  • HVDC transmission from energy source to consumer
    Finding efficient, cost-effective and environmentally friendly ways of transmitting electricity generated can be almost as important as generating the electricity in the first place. Peter Jones and Bo Westman look at HVDC Light.

Top 5 Stories

News

Siemens to provide HVDC link for German offshore wind farms

15 June 2010

Siemens Energy and Prysmian Powerlink will connect two North Sea offshore wind farms to the German grid using a high voltage direct current (HVDC) link for transpower.

The order awarded to the BorWin2 consortium is worth more than €500 millio.

The Veja Mate and Global Tech 1 offshore wind farms, which will have a combined power generating capacity of 800 MW, will be connected to the grid via a submarine cable link carrying HVDC. The offshore wind farms are located approximately 125 km offshore – northwest of the island of Borkum.

The converter will be installed on an offshore platform, where the voltage level will be stepped up from 155 kV to 300 kV alternating current (AC) and then converted to direct current (DC) at the same voltage level.

The platform will accommodate all the requisite electrical equipment for the HVDC converter, primarily the converter itself, two transformers, four AC cable compensation reactors and high-voltage gas-insulated switchgear (GIS).

The Siemens Wind Power Offshore Substation (WIPOS) will be designed as a floating, self-lifting platform. It will be towed by tugs to its destination at sea, where the water is about 40 m deep. By virtue of its design a large heavy-duty crane vessel is not needed to lift the topside onto its foundation.

The wind power will be transported via submarine and land cable to Diele near Papenburg, where an onshore substation will reconvert it from DC to AC for further transmission and distribution within the 400 kV AC grid.

The design and engineering phase for BorWin 2 will be completed by mid-2011. The onshore substation will be built in 2011, with installation of the offshore platform planned for mid-2012. Cable laying is scheduled for completion in 2012 and the whole transmission link is expected to begin operation in 2013.

 

This article is featured in:
Energy infrastructure  •  Wind power

 

Comment on this article

You must be registered and logged in to leave a comment about this article.